Internally here within the ISS Payloads Office, as of 1100 AM USA CDST / 1800 Italia, I have been informed of the following:
-
Flights HTV-2, ULF-6 / STS 134 and ULF-5 STS 133 will slip;
-
Paperwork to confirm the flight slips is expected to be signed "shortly";
-
An announcement of the flight slips is expected during the week 19 - 23 April 2010;
-
HTV-2 will slip six months from Jan 2011 to July 2011;
-
ULF-6 / STS 134 will slip from 29 July 2010 to February 2011;
-
ULF-5 / STS 133 will slip from September 2010 to October 2010. For the ELITE-S2 team, as soon as I get word on the status of the ULF-5 bench review, still planned for 27 April 2010, I will update you. For the Vittori-Six (V-6) ULF-6 / STS 134 team, I hope to have more information for the SIT, Tuesday, 20 April 2010 especially concerning the status of the Flight Safety Data packages. J i m
JAMES J. PELOSI, Ph.D
ISS Payloads Office, Space Operations Research
The Johnson Space Center, B 4 S, # 3207-B
2101 NASA Parkway, Houston, Texas 77058