Voglio ricordare soltanto anche se si sta andando off topic che nel contratto CCtCAP non si fa cenno a requisiti temporali.
Requirements:
The Contractor shall complete the design, development, test, evaluation, and certification of an
integrated CTS capable of transporting NASA crew to and from the ISS, in accordance with the
design reference missions and the certification standards and requirements specified in this
contract. Certification of the CTS shall be determined by NASA. The Contractor shall provide
special studies for risk reduction and other purposes related to its CTS, to the extent ordered under
CLIN 003 of this contract. The Contractor shall also provide complete, initial Post Certification
Missions to and from ISS including ground, launch, on-orbit, return and recovery operations, as
ordered by IDIQ tasks under this contract.
(a) The Contractor shall provide all facilities, resources, personnel, items or services necessary to
perform the requirements specified in Section B, Supplies or Services and Prices/Costs (except for
Government furnished property as listed in clause G.6, NFS 1852.245-76, List Of Government
Property Furnished Pursuant To FAR 52.245-1 and Government Furnished Services and Data as
listed in clause H.12) in accordance with the following:
Attachment J-01, Integrated Crew Transportation System Requirements
Attachment J-02, Data Requirement Deliverables (DRDs)
Attachment J-03, Contract Performance Work Statement (PWS) – To be proposed by Offeror
Attachment J-03, Appendix A, Milestone Acceptance Criteria and Payment Schedule – To be
proposed by Offeror
(b) Section C incorporates Attachments J-01, J-02 and J-03 into the Schedule. In case of a
conflict, Attachment J-01 shall take precedence over Attachments J-02, and J-03. Attachment
J-03 shall take precedence over Attachment J-02.